Building for Nature: A Developer’s Technical Guide to Biodiversity Net Gain (BNG)

by | Nov 19, 2025 | Biodiversity Net Gain

The introduction of Biodiversity Net Gain (BNG) marks a pivotal shift in planning and development in England. No longer is environmental mitigation just a cost; it’s a mandatory, quantifiable obligation to leave nature at least 10% better off than before development.

For developers and planners, understanding the mechanics of BNG is crucial, as securing a BNG strategy is a pre-commencement condition for many planning permissions. Here is a breakdown of the key technical elements you need to master.

1. What Triggers the BNG Obligation?

BNG applies to most planning applications in England, but the rollout and specific exemptions are important to note:

  • Mandatory Start: Compulsory for major planning applications since February 12, 2024, and for smaller applications since May 2, 2024.
  • Exemptions (Avoidance Strategy): You must state which exemption you are relying on if you do not submit a BNG plan. Key exemptions include:
    • Householder Applications: Typically small extensions or changes to existing homes.
    • De Minimis Exemption: Applies if the development affects less than 25 square metres of area habitat, less than 5 metres of watercourse, less than 5 metres of hedgerow, and no Priority Habitat.

2. The Core of BNG: The Biodiversity Metric

The entire BNG requirement is based on a quantifiable score measured in Biodiversity Units. This calculation determines how much habitat you lose and, consequently, how much you must create.

The Calculation for Habitat Loss (Baseline Score)

The baseline score for your site (within the red line boundary) is calculated by an ecologist using four key factors:

FactorDescriptionScoring
AreaThe size of the habitat (in hectares).Directly measured.
DistinctivenessThe rarity of the habitat (e.g., concrete vs. rare grassland).Scored 0 (Very Low), 2 (Low), 4 (Medium), 6 (High), or 8 (Very High).
ConditionThe quality of the habitat.Scored 1 (Poor), 2 (Moderate), or 3 (Good).
Strategic SignificanceUplift if the habitat aligns with a Local Nature Recovery Strategy or similar plan.Multiplier of 1.15 if relevant; otherwise, 1.0.

 

  • Note on Habitats: The BNG Metric uses 132 distinct habitat types (flora and geology based). Animals are not scored directly.
  • Linear Habitats: Hedgerows and watercourses are calculated separately using length instead of area and must also achieve a 10% gain.

3. Securing the 10% Gain: The Mitigation Hierarchy

Developers must follow a strict Biodiversity Gain Hierarchy when deciding how to achieve the +10% uplift. The local planning authority (LPA) assesses compliance with this sequence:

  1. Avoid: Do not cause loss to medium or higher distinctiveness habitat.
  2. Mitigate: Minimise the loss of habitat where avoidance is impossible.
  3. On-Site BNG (Preferred):
    • Enhance existing on-site habitat first.
    • Create new on-site habitat second.
  4. Off-Site BNG (Second Resort): Create or enhance habitat elsewhere.
  5. Statutory Credits (Last Resort): Purchase government credits.

The Complexity of Replacement Habitat (The Multipliers)

When calculating the score for the new replacement habitat (on-site or off-site), the score is discounted using three multipliers. This means you nearly always need significantly more land to replace the units you lost:

MultiplierPurposeImpact on Score
TemporalPenalises the score based on the time it takes for the new habitat to reach its target condition (e.g., a four-year creation time will significantly reduce the initial unit value).Forces developers to dedicate more land to meet the target unit number.
DifficultyPenalises the score if the target habitat is difficult to create (e.g., recreating rare habitats might have a multiplier as low as 0.1).Discourages the creation of unrealistically complex habitats for unit gain.
SpatialPenalises the score based on distance from the development site.If habitat is two or more local authority areas away, the score is multiplied by 0.5 (a 50% penalty). Encourages local replacement.

4. Key Technical Mechanisms

A. The Biodiversity Gain Plan (BGP)

The BGP is the critical document that must be approved by the LPA before commencement. It details:

  • The habitat loss score (the deficit).
  • The final habitat gain score (+10% or more).
  • The specific location and type of units being used (on-site, off-site, or credits).
  • Evidence that the BNG has been secured for at least 30 years.

B. Securing the BNG Obligation

The long-term delivery and maintenance of the habitat units must be secured via a legally binding agreement:

  • On-site BNG: Usually secured via a Section 106 Agreement or a new mechanism called a Conservation Covenant. The LPA often prefers agreements over planning conditions for monitoring fee collection.
  • Off-site BNG: Must be secured by the landowner of the off-site area, typically through a Section 106 Agreement or Conservation Covenant. Once the units are registered and allocated to your development, your obligation is largely discharged.

C. Off-site BNG Register

All off-site BNG sites must be placed on a National Register. This prevents double counting and tracks the allocation of units. Developers relying on off-site units must ensure their units are formally allocated on this register.

D. Habitat Management and Monitoring Plan (HMMP)

Accompanying any securing agreement (S106/Covenant), the HMMP sets out the specific actions, targets, and monitoring schedule required to ensure the newly created or enhanced habitat reaches and maintains its target condition for the full 30-year period.

5. Avoiding Costly Traps

  • Habitat Degradation: Do not intentionally degrade habitat on your site prior to application to lower the baseline score. The LPA can force you to calculate BNG based on the condition before the degradation occurred.
  • High Distinctiveness Habitats: Avoid building on High (Score 6) or Very High (Score 8) distinctiveness habitats if possible. High distinctiveness must be replaced with the same habitat type, and Very High distinctiveness requires bespoke compensation, making the BNG process much more complex and expensive.
  • Statutory Credits: As a last resort, purchasing government credits is extremely expensive (minimum cost of £84,000 per unit), reinforcing the need to find on-site or off-site solutions first.